Spruce Court

16 Dec 2021
Enabling works

Enabling works will begin at Spruce Court.

14 Mar 2022
Flat conversions

Works on flats at Spruce Court will commence

28 Mar 2022
Sales properties

Full works on all sales properties will commence.

06 Jun 2022
Remaining properties

Full works on the remaining properties will commence.

01 Nov 2022
6, 21 and 22 demolition

Works to demolish 6, 21 and 22 commence

01 Jan 2023
Demolitions and external home frontages complete

Demolition of 6, 21 and 22 finished, render and cladding applied to homes except those next to demolition units

22 Sep 2023
Work starts on externals

For driveways, fencing and roads

01 Dec 2023
Solar power installation

Solar power and batteries installed in our homes

01 Feb 2024
Commence internal Court works

Commence internal works for court side drives, roads and gardens.

01 Mar 2024
Flat conversions

Complete and let flat conversions

17 May 2024
Complete internal Court works

Internal works for court side drives, roads and gardens complete

28 Jun 2024
Barrier installation

Install barriers to prevent vehicles accessing the football field

01 Jul 2024
New road

New road to Spruce court completed.

Jump to another section

Almond Court flats

Key dates Key dates

Lilac Court flats

Key dates Key dates

Aspen Court

Key dates Key dates

Spruce Court

Key dates Key dates

Laurel Court

Key dates Key dates